Bathroom Remodeling Timeline
OC Contractor Bathroom Remodeling works just one job at a time. Your project takes top priority and we won't pull off of your job to work on other projects. Our state-licensed working foreman is on your job every day attending to all details so you don't have to.
Planning, scheduling, and selection of materials takes place 2 - 3 weeks prior to beginning construction. OC Contractor will be with you every step of the way, from our first meeting, through product selection, and completion of construction.
Day 1
- Dumpster arrives
- Place protective drops and plastic
- Remove items
- Repair wood damage
- Plumbing
- Electrical
- Prepare floor
- Install shower pan or bathtub
- Greenboard walls
- Clean up
Day 2
- Install vanity cabinet
- Finish electrical
- Install walls around shower or tub
- Repair/patch walls
- Clean up
Day 3
- Finish walls around shower or tub
- Install plumbing fixtures, support bars
- Install sinktop, bowl, faucet
- Install medicine cabinet, mirrors, light fixtures
- A1 Shower Door measures for glass enclosure
- Clean up
Day 4
- Install flooring
- Install baseboards
- Install toilet
- Install remaining odds and ends
- Clean up
Day 5
- Install toilet (if the flooring was tile)
- Install baseboard (if the flooring was tile)
- Clean up
- ALL INSTALLATIONS COMPLETE