Kitchen Remodeling Timeline
OC Contractor Bathroom Remodeling works just one job at a time. Your project takes top priority and we won't pull off of your job to work on other projects. Our state-licensed working foreman is on your job every day attending to all details so you don't have to.
Planning, scheduling, and selection of materials takes place 2 - 3 weeks prior to beginning construction. OC Contractor will be with you every step of the way, from our first meeting, through product selection, and completion of construction.
Day 1
- Dumpster arrives
- Place protective drops and plastic
- Remove all kitchen items
- Prepare floor
- Clean up
Day 2
- Plumbing
- Electrical
- Repair/ patch walls
- Clean up
Day 3
- Finish rough plumbing
- Finish rough electrical
- Finish Repairing drywall - plaster holes
- Start laying out / installing cabinets
- Clean up
Day 4
- Start installing cabinets
- Start laying out appliances
- Clean up
Day 5
- Install cabinets doors and drawer guides
- Laying out appliances
- Make custum countertop templates
- Install plumbing shout offs
- Clean up
Day 6
- Finish installing cabinets and crown moldings
- Install flooring
- Install baseboards
Day 7
- Prep for installing appliances
- Finish installing baseboards / floor treatments
- Prepare for countertop installation
- Clean up
Day 8
- Install countertops and backsplashes
- Install appliances / cooktop / oven / range hood / dishwasher etc.
- Install faucet / garbage disposal / plumbing etc.
- Finish electrical
- Clean up
Day 9
- Finish Instaling appliances / cooktop / oven / range hood / dishwasher etc.
- Finish any plumbing
Day 10 - 11 - 12
- Place protective drops and plastic
- Prep / start drywall patching & texturing
- Start Priming and painting
- Finish paint
- Clean up
Day 13
- Install / finish remaining odds and ends
- Install electrical plates and Recessed light trims ext.
- Finish any fine details
- Get A Happy Testimonial from you